A truck is loaded to haul away the last of the sludge from the lagoon at Marion's wastewater treatment plant on Benson Brook Road on Monday morning. The operation, overseen by Methuen Construction, is expected to be completed this week, paving the way for the grading and relining of the lagoon by the end of October. Photos by Mick Colageo

Benson Brook Road

A truck is loaded to haul away the last of the sludge from the lagoon at Marion's wastewater treatment plant on Benson Brook Road on Monday morning. The operation, overseen by Methuen Construction, is expected to be completed this week, paving the way for the grading and relining of the lagoon by the end of October. Photos by Mick Colageo